· Construction workers poured 1/3 of the floor.
· In the next two weeks the rest of the floor will be poured.
· Once the floors are in they will lay blacktop on the north and east sides of the building.
· Grass will be sown between the driveway and the back of the gym and also along the driveways. We hope this will be done yet this fall.
· Next week new permanent fences will be installed along with rolling gates.
· The small white shed in the corner of the playground will be removed.
· A sidewalk is being installed along the south side of the east parking lot and the soccer field. The government is forcing us to do this.
· A new sidewalk will most likely be installed along 26th street.
· Framing will begin as soon as the floor is completely poured. |